Appendix E2

South Hams District Council

Business Case Outline

 

The Business Case is used to obtain management commitment and approval for investment in business change including projects and programmes, through rationale for the investment.

The Business Case provides a framework for planning and management of the business change. The ongoing viability of a project or programme will be monitored against the Business Case.

 

Purchase of Bio shredder for Grounds Maintenance

 

Senior Responsible Officer:

Dale Cropper

Project Sponsor

ELT Member:

Steve Mullineaux

Date Updated:

(21/10/2022)

Version:

1.0

Programme/Project Description:

Purchasing of a new bio shredder to support the community composting groups, and the longer-term strategy for improving biodiversity across South Hams

Reviewers:

 

Author(s):

Dale Cropper – Operations Manager

 

 

Guidance

 

An outline business case is a document setting out the initial justification for investment of resources (people, time and money) into a project or change being considered. This outline business case is to be completed at the initial idea stage of any project.

 

Once approval has been given to the outline case, solution design work will begin and the project will undertake a more detailed Business case setting out full implementation and business running costs, the benefits of implementation and an assessment of how implementation would be managed and the associated change risks and issues. 

 

Capital projects will be scored on the following criteria:

 

•           Health and Safety compliance

•           Essential to keep operational assets open

•           Fit with the Council’s Delivery Plans for ‘Better Lives for All

•           To rationalise service delivery or service improvement

•           To generate income, capital value or to reduce revenue costs

 

It is important that future bids for capital are aligned with the review of the thematic delivery plans and aims within ‘Better Lives for All’.

 

 

 

 

 

1.         Project Summary – Project objectives and what it aims to achieve.

 

Currently we use a bio shredder to support 6 local community composting groups. The existing bio shredder is coming to the end of its life and needs significant repairs. By purchasing a new unit, we can ensure that we can continue to service these community groups and their composting needs. As well as this, it will also support reduction in the amount of green waste generated on sites being tipped, which costs around £50 a tonne. Instead, we will be able to reuse this material for mulch and potentially composting, ensuring a greener outcome.

 

 

2.         Why we need the Project – Background and problem/opportunity to be addressed.

 

The bio shredder grinds, mulches, and mixes biodegradable products from grass mowing, roots, tree lopping’s and soil, and reduces the volume of material to allow it to be reloaded or applied elsewhere.

Without this purchase, we would be unable to continue with providing this support to community groups and will see increased green waste tipping costs. Once the full biodiversity strategy has been rolled out, it will also support delivery of this through being able to reduce green waste tipping costs.

 

3.         Project Scope – State what’s IN and OUT of Scope.

 

Purchase of a new unit is the only in scope requirement.

 

 

4.         Benefits – Brief indication of any potential financial and non-financial.

 

 

 

5.         Links and Dependencies – To other projects currently live.

 

Link to the Waste Community Composting Project and the Biodiversity Report.

 

 

6.         Risks – Note of any significant potential risks.

 

The existing unit is at the end of its life and any breakdown could mean that we are both unable to support local composting groups but also that we will see substantial increases in green waste volumes and tipping costs as we are unable to process our green waste.

 

7.         Project Resources – What people will the project need?

 

Funding of £65,000 for the purchase

Support from Dale Cropper and Scott Rogers in procuring a new unit.

 

 

8.     Explain how the project meets the five criteria listed below.

 

Health and Safety compliance

 

Will reduce any risk of workplace injury by having a unit that is fit for purpose.

Essential to keep operational assets open

Without a new unit we will be unable to maintain current operations.

Fit with the Council’s Delivery Plans for ‘Better Lives for All’

Supports Quality Council Services - ensuring that we make the best use of the budget available, to ensure value for money.

Will support the Climate and Biodiversity targets - ensuring that Climate Change and Biodiversity are priorities for all Council services, creating an environment where people and nature thrive together.

To rationalise service delivery or service improvement

Will ensure green waste tipping volumes and costs are kept to minimal standards.

To generate income, capital value or to reduce revenue costs

Will allow us to offer this service to towns and parishes and more community groups to generate income.

 

 

 

Capital costs and revenue implications

 

In the table below, please detail the capital budget requirement over the next three financial years as well as any revenue implications (maintenance, repairs, etc…)

 

Financial year

Capital cost

Revenue implications

2023/24

£65,000

 

Total cost

£65,000

 

 

 

Please detail in the box below how this project will be financed:

 

Financial Year

Capital grants/ contributions

S106

Reserves

Capital receipts

No funding source identified

2023/24

 

 

£65K

New Homes Bonus funding